Medical:

UC Irvine Medical Center, Orange
101 The City Dr S, Orange, CA 92868

 Remodel of existing patient restrooms and lounge (including asbestos removal), demolition and installation of new wall finishes in the patient lounge.
Western Medical Center, Santa Ana
1001 N Tustin Ave, Santa Ana, CA 92705

New 43,650 SF, two-story hospital administration building with data center, associated site work and landscaping.
Centinela Hospital Medical Center, Los Angeles
555 E Hardy St, Inglewood, CA 90301

This negotiated OSHPD project included demolition, new radiology exam room with lead shielding, fire sprinklers, control room, new GE Discovery XR656 Imaging System, dressing rooms, restroom, and ADA upgrades.
Glendora Community Hospital, Glendora
150 W Rte 66, Glendora, CA 91740

This OSHPD project consisted of the replacement of overhead lights in two operating rooms including new above ceiling structural support systems to meet seismic mounting upgrade requirements.
San Dimas Community Hospital, San Dimas
1350 W Covina Blvd, San Dimas, CA 91773

This project consisted of a new data room with a split system and the installation of a new telemetry monitoring system in the ER and ICU and includes behind wall seismic mounting upgrades.  The project also includes electrical service to the data room.
Hycor Biomedical, Irvine
7272 Chapman Ave, Garden Grove, CA 92841

Design and construction of new lab area for testing allergic reactions to skin tissue, new offices and a new elevator, totaling 4,000 SF.
PIH Health Hospital-Downey, Downey
11500 Brookshire Ave, Downey, CA 90241

This OSHPD project consisted of an approximate 25,000 SF Refresh throughout the 2nd. floor patient rooms and support services areas of an active hospital and included new flooring, wall covering, ceiling tiles, casework with seismic backing, finishes and paint. The project also included remodeling of two nurses stations, radiology suite and pharmacy.
Suncrest Hospital, Torrance
4025 W 226TH ST, TORRANCE, CA, 90505

This OSHPD project consisted of a remodel of the main hospital entrance and the installation of a new 2-hour rated corridor in a fully operational hospital.
Marina Del Rey Hospital, Marina Del
4650 Lincoln Blvd, Marina Del Rey, CA 90292

This OSHPD project included the installation of a new 500 KW (480 Volt) emergency generator.  The project included underground trenching for the utility feed into the hospital and associated hardscape.
InterCommunity Surgical, Yorba Linda
This OSHPD project consisted of a 22,000 SF remodel including new lab areas, sterilization areas, boiler units, lunch room, conference room, conference room, executive offices, showroom and lobby.
North Orange County Community Clinic
Installation of new utility services to two existing modular buildings including form-place-finish of new concrete stairs and sidewalks, and new hand railings.
Regency Health Services, Tustin
Demolition and new construction of 10,000 SF of medical office space.  The project included new electrical wiring, drop ceiling, paint, fixtures, cabinetry, and extensive reworking of the HVAC system.
Show More